Project details:
- Precast concrete and structural concrete works
- Earthworks
Project outcomes:
- Laying the concrete pad and tunnel
- Erection of the steel-framed insulated metal-roofed building 90m by 25m, pre-fabricated in Sweden, and clad with precast walling manufactured in Adelaide.
Achievement:
- M&B Civil took four weeks less to complete the project than another supplier that built a matching substation across the border in Victoria
Building Work Contractor’s Licence Number BLD 43032