Berri

High Voltage switching Building and Substation.

Project details:

  • Precast concrete and structural concrete works
  • Earthworks

Project outcomes:

  • Laying the concrete pad and tunnel
  • Erection of the steel-framed insulated metal-roofed building 90m by 25m, pre-fabricated in Sweden, and clad with precast walling manufactured in Adelaide.

Achievement:

  • M&B Civil took four weeks less to complete the project than another supplier that built a matching substation across the border in Victoria

 

Building Work Contractor’s Licence Number BLD 43032